All projects

Industrial

Refrigeration electrical infrastructure

We project managed and delivered a 12-week electrical infrastructure programme for refrigeration, with supply changeovers carried out in phased night works.

Rooftop cable tray and support frames for electrical cables and refrigeration pipework
Sector
Industrial
Programme
12 weeks

Project overview

Coordinating infrastructure and phased changeovers

The works combined new LV submains and terminations with approximately 1,000 metres of cable tray. We used two tonnes of Unistrut to construct H-frames supporting both electrical installations and refrigeration pipework. Existing refrigeration supplies were removed and new supplies installed over phased nights, avoiding disruption to the general public.

Explore industrial electrical services

What we delivered

  • Project management throughout the 12-week programme
  • Installation and termination of LV submains
  • Approximately 1,000 metres of cable tray
  • H-frame construction using two tonnes of Unistrut for electrical services and refrigeration pipework
  • Removal of existing refrigeration supplies and installation of new supplies
  • Phased night works to avoid disruption to the general public

Next project

Walstead UK — power infrastructure upgrade